Pumpi project

Located in the Democratic Republic of Congo, in the province of LUALABA within an important zone of copper reserves, the Pumpi project presents itself as a large-scale deposit.

In partnership with the Chinese group Wanbao Mining, Managem Group has launched the construction of a mining complex, consisting of 32 operating permits covering a heritage of 25.6 km2.

With its strong geological potential, Pumpi project perfectly embodies Managem's strategic ambitions in Africa. More than 10 years of research and major exploration work carried out by geologists from Managem have led to the discovery of mineral resources of 148,500 T of Cobalt and 778,000 T of copper.

While the inauguration ceremony of the project took place in March 2019, the main civil construction work started in May 2019. In September 2020, Pumpi went into production and delivered its first copper cathodes.